Section 650d German Civil Code on construction change orders: interim relief and its limits – Higher Regional Court Celle, judgment of 14 May 2025 – 14 U 238/24

The Higher Regional Court stresses: only a contractor who has submitted a clear change-order offer can quickly enforce disputed claims through the statutory 80 per cent rule.

Attorney Ruhlmann

Unpaid change order: liquidity pressure on the construction site

The customer (owner) asks for a changed or additional service on site. The contractor carries it out, orders materials, deploys staff and claims extra payment for it – the change order (Nachtrag). If the customer does not pay, the contractor has to finance the work itself in the meantime. By the time an action in the main proceedings is decided, it may be too late to protect liquidity while the project is still under way.

This is where Sections 650b to 650d of the German Civil Code (BGB) come in. If the customer requests a change to the agreed work or an additional service needed for the work to succeed, the parties must first try to agree on the change and on the extra payment. For that, the contractor must submit a comprehensible offer for the additional or reduced remuneration. If no agreement is reached within 30 days, the customer can order the change unilaterally in text form (Section 650b BGB). Section 650c BGB then governs the remuneration: what counts is the additional or reduced costs actually required, plus reasonable allowances for general business costs, risk and profit.

Where the remuneration for a change order is disputed and the work has already been done, the contractor can apply for an interim injunction for a provisional payment. For interim payments, the contractor can in principle claim 80 % of the additional remuneration stated in his offer (Section 650c(3) BGB). The customer does not have to bring an urgent application of his own to defend himself: he can object that there is no effective order, no claim under Section 650c BGB or no conclusive change-order calculation. If he wants the question clarified actively, he can in principle also seek a negative declaratory injunction.

Section 650d BGB: easier interim relief for construction change orders

Section 650d BGB is not a separate procedure and gives no payment claim of its own. It simply makes it easier to obtain an interim injunction in change-order disputes. For an interim payment injunction for additional remuneration, the dispute must normally follow the statutory sequence: the customer requests a change, the contractor submits a change-order offer, no agreement is reached, and the customer then orders the change unilaterally in text form under Section 650b(2) BGB. Section 650c BGB then governs the adjustment of the remuneration. Once construction has begun, the contractor does not have to make a separate case for an injunction in this dispute. Where the contract was merely changed by agreement, a contractual payment claim does exist, but the special relief under Section 650d BGB does not in principle apply to it.

Without Section 650d BGB, the applicant would also have to explain why an immediate court decision is necessary and why the main proceedings cannot be awaited. A provisional payment would then normally be available only as a performance injunction under particularly strict conditions, because it effectively anticipates the main case. Section 650d BGB, by contrast, allows liquidity to be secured provisionally; whether the change-order remuneration is finally owed is still decided in the main proceedings.

A conclusive presentation of the case, and making the claim credible, remain indispensable. The contractor must set out clearly the construction contract, the customer's request for a change, his earlier change-order offer, the failed agreement, the subsequent order in text form, the work done and the calculation of the additional remuneration. The presumption of urgency in Section 650d BGB can also be rebutted. Even an interim payment injunction does not finally decide the remuneration dispute: the main proceedings remain open.

Higher Regional Court Celle: not every construction change falls under Section 650d BGB

The judgment of the Higher Regional Court (OLG) Celle of 14 May 2025 – 14 U 238/24 shows clearly where the limits of interim relief under Section 650d BGB lie. The contractor had applied for an interim injunction against the customer for provisional payment of two disputed change-order items. The customer defended himself, among other things, by arguing that the conditions for a statutory adjustment of remuneration under Section 650c BGB were not met.

The court treated the two items differently:

  • For the cost of disposing of drilling water, reliance on Section 650c BGB failed because the contractor had given the customer no sufficiently specific change-order offer. The wording “upon proof” did not reveal what additional remuneration might be due.
  • For the instruction to reduce the daily filling quantity, the contractor claimed extra payment: because of the lower daily output, it argued, staff and equipment had to be kept available for longer, so its costs per unit of work rose. The court nevertheless found no relevant change to the work under Section 650b BGB. In its view, the instruction concerned mainly the construction process and timing, not the content of the works owed under the contract. Without an order under Section 650b BGB, no adjustment of remuneration under Section 650c BGB can arise from it either.

The VOB/B (the German standard terms for construction contracts) had been agreed in this case. Within its scope it can modify statutory construction contract law, but here it did not displace Section 650c BGB: Section 16(1) VOB/B only regulates interim payments for services properly rendered under the contract; it does not provide for a provisional invoice of 80 % of the offered additional remuneration. Separate claims for additional remuneration under Section 2(5) or (6) VOB/B can exist alongside. They open the door to the eased interim relief under Section 650d BGB, however, only if the dispute is really about an order under Section 650b BGB or the resulting adjustment of remuneration under Section 650c BGB.

Higher Regional Court Celle: waiting cost the urgency

The judgment contains a second, independent point: on the drilling-water item, the court added that even if Section 650d BGB did apply in principle, the presumption of urgency had been rebutted by the long delay. The court thus illustrates the principle described above that the presumption of urgency can be rebutted.

The customer had refused to pay from the start, yet the contractor waited more than a year before applying for urgent relief on this item. That in itself rebutted the presumption of urgency. The contractor then had to set out and make credible a ground for an injunction under the general rules of Sections 935 and 940 of the Code of Civil Procedure (ZPO). This failed: a general reference to running costs and falling liquidity was not enough for the payment injunction, which is admissible only exceptionally because it anticipates the main case. The contractor had shown neither specific, unavoidable disadvantages nor impending insolvency.

Conclusion

Contractors should apply for urgent relief under Section 650d BGB only once they can prove the statutory sequence without gaps: the customer's request for a change, a verifiable change-order offer, failed agreement, a subsequent order in text form, work already done and a comprehensible calculation. Despite the presumption of urgency, they need to act promptly after a final refusal to pay; waiting too long can make it lapse.

Customers should consider carefully, before ordering a change unilaterally, which service they actually want to change, and should put the order clearly in text form after a failed agreement. Against a payment application, they should in particular check whether a change to the content of the works was ordered at all. A mere wish for a change, a change of contract by agreement, or an instruction that concerns only the construction process and timing will normally not be enough. If a sufficiently specific change-order offer is also missing, the contractor cannot base its additional remuneration on Section 650c BGB and the relief under Section 650d BGB; it would then have to set out and make credible the special urgency under the general rules.

The judgment shows how much compliance with formal requirements matters for interim relief in construction contracts.

In disputes over additional remuneration, construction delays or conflict resolution during construction, KANZLEI RUHLMANN in Berlin represents contractors and customers as a litigation firm for construction and real estate law, resolutely before the competent construction-law chambers.

This article is for general information only and does not constitute legal advice in an individual case. It does not replace individual legal advice.